Skip to Main Content
ajax loader animation
ajax loader animation

PowerReady Incentive Dashboard

Get information on current incentive levels and program progress to goal. Details updated monthly. 

Current Incentive Caps

Please note that your eligibility tier provides the maximum incentive amount; your actual incentive will be determined in the Program Agreement (PA) stage, after you have received your energy service ruling. The incentive amount will vary depending on the maximum incentive eligibility level, total site costs, program budgets, and the general competitiveness of the project when compared to other projects.

Level 2 Plug Cost Caps

Incentive Cap for Program Eligible Costs (Customer + Potential Utility Costs; All values shown are “Up to”)

Incentive Tier

Base Cost
Cap

Speed Bonus

Large Project Bonus
(25+ plugs)*

Max Available
Cost Cap

Future Proofing
Bonus

Up to 50%

$5,000/per plug

$1,000/per plug

$1,500/per plug

$7,500/per plug

10% of eligible costs

Up to 90%

$9,000/per plug

$1,800/per plug

$2,700/per plug

$13,500/per plug

10% of eligible costs

Up to 100%

$10,000/per plug

$2,000/per plug

$3,000/per plug**

$15,000/per plug

10% of eligible costs

*Large Project Bonus – Project must be 25 plugs or more, can only be applied to the first 100 plugs.
**The 25-plug minimum is waived for this tier (up to the first 100 plugs).

DCFC kW Cost Caps

Incentive Cap for Program Eligible Costs (Customer + Potential Utility Costs; All values shown are “Up to”)

Incentive Tier

Base Cost Cap

Speed Bonus*

Load Mgmt Bonus**

Max Available Cap

Charger Hub
Path Bonus***

Max Available Cost Cap

Future Proofing Bonus

Up to 50%

$400/kW

$50/kW

$25/kW

$475/kW

N/A

N/A

10% of eligible costs

Up to 90%

$720/kW

$90/kW

$45/kW

$855/kW

$225/kW

$945/kW

10% of eligible costs

Up to 100%

$800/kW

$100/kW

$50/kW

$950/kW

$250/kW

$1,050/kW

10% of eligible costs

*Speed Bonus: If installing a L2 project, your project needs to complete a successful work verification within 4 months of signing the Program Agreement. If installing a DCFC/Mixed plug project, your project needs to be ruled “Service Adequate” and must complete work verification within 6 months of signing the Program Agreement. Cannot be combined with Interconnection bonus.
**Load Management Bonus: Participants must install Hardware Load Management equipment (e.g., disconnect switches, relays, rectifiers, circuit breakers, power cabinets) to qualify for the bonus. DCFC plugs must maintain a minimum output of 50 kW after load reduction. This bonus may be paired with Speed Bonus if service adequate.
***Interconnection Bonus: Service Inadequate/ Public 10+. Must have significant interconnection costs such as new service or block house. Cannot be combined with any other bonus.

Waitlist Status

L2 Disadvantaged Community (DAC) waitlist

We are currently working through the waitlist of active projects that applied for the “up to 100%” incentive tier. We are currently not accepting any additional projects for this waitlist.

L2 General Program Timed Release

We are currently committing projects up to our regulatory target (approximately 21,000 L2 plugs). We are currently accepting new projects and applications will proceed off the standby list on a monthly basis.

DCFC general program waitlist

No waitlist


Plug Pipeline*

Installed Complete

Installed Validaton

Committed

In Pipeline

Stand-By

Not Yet Applied

End Target

All L2 Plugs

17,230

840

2,880

19,090

0

0

21,371

Up to 50%

9,760

480

1,200

7,770

Up to 90%

4,680

350

1,470

5,320

Up to 100%

2,690

0

170

0

Mixed Tier

100

10

50

6,000


Plug Pipeline*

Installed Complete

Installed Validaton

Committed

In Pipeline

Stand-By

Not Yet Applied

End Target

All DCFC Plugs

720

160

770

3,240

0

0

3,127

Up to 50%

380

10

90

40

Up to 90%

170

50

340

550

Up to 100%

140

90

310

740

Mixed Tier

30

10

10

1,910

Installed includes both completed projects and projects notified as fully installed by participant, but not yet validated by Con Edison.
*Values are rounded to the nearest 10 plugs

Budget Pipeline ($M)

Installed Complete

Installed Validation

Committed*

Estimated in Pipeline**

Not Yet Applied***

End Target

L2 Funds

$164.20

$6.90

$26.10

$105.80

$0.00

$237.80

Up to 50%

$66.70

$2.70

$7.70

$47.70

Up to 90%

$55.50

$4.10

$15.20

$58.10

Up to 100%

$40.80

$0.00

$2.00

$0.00

Mixed Tier

$1.10

$0.10

$1.10

$0.00


Budget Pipeline ($M)

Installed Complete

Installed Validation

Committed*

Estimated in Pipeline**

Not Yet Applied***

End Target

DCFC Funds

$24.40

$6.90

$75.60

$162.20

$109.40

$347.20

Up to 50%

$7.00

$0.30

$1.90

$2.00

Up to 90%

$9.20

$3.90

$32.30

$58.10

Up to 100%

$7.50

$2.00

$39.10

$102.10

Mixed Tier

$0.70

$0.60

$0.30

$0.00

Installed includes all funds that are committed, including projects that are paid out and projects to which Con Edison has committed funds via signed Payment Agreements.
* Funds committed to projects not yet installed are subject to change once incentives are finalized and paid out.
**Estimate of funds it would take to incentivize all plugs in the pipeline, including the wait list, and this value may exceed the program authorized budget.
*** Not yet applied captures the estimated budget available if all applied projects were to be installed. Some applied projects will not move forward so interested participants are encouraged to apply since additional budget may be available.