Step-by-Step Project Guide

Guidance for electrification upgrades and gas service maintenance, plus safety requirements for renovations or demolitions.

hero-a11y

About

Planning a renovation, service upgrade, or demolition? Review the process step by step — from submitting a work request through the Project Center to scheduling inspections and disconnecting gas service.

Back to top

Process Overview

Back to top

From scoping the job and breaking ground to final inspections and approvals, get an in-depth look at the resources, requirements, and best practices for every step of the process:

If your project includes demolition, read through the Demolition Requirements before you begin.

Download PDF

Demolition Requirements

Requesting the removal of Con Edison services for a demolition project involves three basic steps: gathering the required information, requesting a review of the removal, and then receiving a confirmation from us.

Back to top

Step 1

You Request to Close the Account

  • Close all Con Edison billing accounts associated with the property.
  • Obtain a notarized letter from the property owner requesting the removal of Con Edison services.
  • Include the property's unique identifier:
    • New York City: Building Identification Number (BIN)
    • Westchester County: SBL/Print Key
  • Provide all Con Edison account numbers and meter numbers associated with the property.

Step 2

We Review

  • After your request is submitted, we will review it to confirm:
    • All required documentation has been received.
    • All associated billing accounts have been closed.
    • Customer, account, and meter information is accurate.
  • Once the review is complete, the request will be processed as a demolition service removal request. If the status of the service cannot be confirmed, we may issue a Gas Investigate Work Request to Gas Operations to verify the condition of the service before demolition work can proceed.

Step 3

You Receive Confirmation

  • After all services have been disconnected in the street, the Energy Services Department will provide a confirmation letter stating that the property's services have been disconnected.
  • The letter will include:
    • The Project Center case number
    • The property's unique identifier (BIN or SBL/Print Key)
    • The service address

Next Steps

Property Owner Guide

Help for property owners starting new energy services upgrades.

Contractor Guide

Explore tools to help keep builds and renovations on track.